Bitumio uses Production Rates to set a baseline for how long a certain type of job should take. This helps standardize how estimates are being created based on expected output from crews. This helps remove some of the ambiguity on how long a job should take and more accurately estimate costs. 


These production rates are averages across several customers who gave permission to share. If you are new to using production rates, use these as a baseline to start determining estimates and these can be edited while you create more estimates. 


ServiceProduction RateUnit
Crackseal High Production8,000Linear Feet per Day
Crackseal Low Production2,500Linear Feet per Day
Sealcoat High Production (Spray)175,000Square Feet per Day
Sealcoat Medium Production (Spray)100,000Square Feet per Day
Sealcoat Low Production (Spray)75,000Square Feet per Day
Sealcoat High Production (Squeegee)100,000Square Feet per Day
Sealcoat Low Production (Squeegee)50,000Square Feet per Day
Slurry10,000Square Yards per Day
Line Striping10,000Linear Feet per Day
Asphalt Paving High Production125Tons Per Hour
Asphalt Paving Medium Production75Tons Per Hour
Asphalt Paving Low Production50Tons Per Hour
Mastic Average800Linear Feet per Day

 

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article